Sirius Minerals

Latest construction news

This section outlines the headline construction schedule over the next five years and provides more details of works that are happening now or coming soon.


Overview:

  • Highways works to improve pedestrian safety in Whitby and access to Woodsmith Mine have been completed on schedule.

  • Site preparation at Woodsmith Mine has commenced and is progressing well. Works include site clearance, screening and soil storage, acoustic and security fencing, drainage works, and construction of the site roads and the shaft sinking platform.

  • Geotechnical investigation works continue to be carried out at the mine site and are on schedule.

  • Site preparation works are now underway at the intermediate shaft site at Lockwood Beck, together with highways works to improve access to the site.

  • The Company is looking to simplify the mine infrastructure and has been in discussion with the local planning authority about minor amendments to the Project, which are outlined below.

More details are available using the links to the right. Please click here for our latest quarterly update.


Woodsmith Mine plans simplified

The proposed amendments will simplify construction, improve efficiency and also reduce some environmental impacts during construction. The primary amendment involves the relocation and reorientation of the approved buildings at the site above re-designed foreshafts. This will enable permanent winders to be installed from the outset, removing the need for two 45m high temporary winding towers during the five-year construction period and the requirement for an access drift.

The change will mean that the footprint of the site buildings will increase slightly, by less than 6%. Building heights will not change and the site will still be screened as before.

It is proposed to relocate some of the water attenuation ponds to the east of the site which means that trees that were going to be removed will be retained.

A Scoping Report has been submitted to the local autority in advance of a Section 73 application which is likely to be submitted this summer.

Limiting impacts

The planning permissions for the Project include a range of planning conditions that cover areas such as traffic movements, noise and site lighting, amongst others. The Company will operate within these limits and will continue to seek to limit the impact of construction on people living, working and visiting the local area wherever possible.

Communication

We will ensure that local residents, businesses, schools and other stakeholders nearby the works are notified and provided with further details before work on each site commences. This will include letters, newsletters, press releases and in some cases public exhibitions.

It is also important to us that people have the opportunity to contact us directly if they have questions or concerns about the Project. We can be contacted on our 24-hour community helpline on 0845 543 8964.

Liaison Group Forum

There are quarterly Liaison Group Forum meetings with local elected representatives that are open to members of the public to attend. The purpose of these meetings is to provide Project updates and receive community feedback. Minutes of meetings are available using the link to the right and future meetings will be publicised on this website.

The next meeting is on Tuesday 11 July 2017, 1.00 – 2.30pm in the Bede Hall, Sneaton Castle Centre, Whitby, YO21 3QN.

Mine

Naming ceremony

Current works

Highways

Construction

Headline schedule

Completed works

Highways

Sirius Minerals

Liaison Group Forum

Update

Newsletter